The Maxiflow Blog

Maxiflow awarded prestigious Manchester Cathedral contract

manchester-cathedral-welcome-1

Photo courtesy of edwin.11 on Flickr

We at Maxiflow are proud to announce that we have been awarded a prestigious new contract with Manchester Cathedral, in partnership with Strutt and Parker.

Following the recent appointment of Bishop David Walker as the new Bishop of Manchester, Maxiflow have been contracted to undertake a full refurbishment of the Bishop’s Residence.

This major project draws together many areas of Maxiflow expertise, including full-scale decorative works, all-new carpeting, an upgrade of the electrical system, the installation of a state-of-the-art heating system and much more.

Maxiflow has plenty of experience in this area, as we have an extensive history of working in partnership with Chester Cathedral, including carrying out a large-scale refurbishment of the heating system in the Bishop’s House in Abbey Square last year.

We will continue to provide coverage of this exciting new contract as the project progresses.

More from the Maxiflow Blog

Step-by-step automated bollard installation at Quarry Car Park in Chester

Maxiflow installing new bollard system at Quarry Car Park in Chester

In a previous blog post, we detailed our installation of a bollard at Abbey Square Gateway. In addition to this high-profile project, Maxiflow were also contracted to carry out the excavation and installation of a new automatic bollard system at Chester’s Quarry Car Park, in partnership with MACS Bollards.

Quarry Car Park is a small, private parking facility off Northgate Street, and is owned by Chester Cathedral. The entrance was previously regulated by a rising barrier arm, which unfortunately proved to be a prime target for vandals.

Faced with the costs and wasted time associated with repairing and replacing the barrier, the Cathedral decided to take a different approach and implement an entirely new automatic bollard system.

Maxiflow diagram of the new bollard system at Quarry Car Park in Chester

The diagram above maps out the area where the new system was installed, and the following points of interest are labelled in the images below:

  1. The bollard itself
  2. The safety induction loops
  3. The control cabinet
  4. The status lights and access control post

Maxiflow installing new bollard system at Quarry Car Park in Chester

The first task involved excavating a trench for the bollard (A). The bottom of the trench was bedded with gravel, and the sides were lined with concrete and cement to give the bollard maximum strength and stability. The bollard itself is housed within a hydraulic mechanism, which enables it to rise and fall smoothly.

To allow for the electrical connections and sensors to be laid along the ground, the existing roadway surface had to be stripped away on either side of the bollard.

Maxiflow installing new bollard system at Quarry Car Park in Chester

During the planning stages, it was noted that ducting installed for the previous barrier arm system could be re-purposed for the bollard. The location marked at (C) connects to the ducts and was chosen to be the site for the bollard system’s control box.

The empty bollard housing (A) in the above photograph demonstrates that the bollard itself is a separate element. If damaged, the bollard can be removed without dismantling the rest of the system.

Maxiflow installing new bollard system at Quarry Car Park in Chester

After smoothing the base, an initial layer of tarmac was laid to protect the underside of the induction loop cabling (B). This cabling is pressure-sensitive and is used to detect the approach and departure of vehicles.

This is an important safety feature, as it ensures that the bollard does not rise up underneath a vehicle. This could damage both the bollard and the vehicle and potentially endanger the driver. Induction loops are a smarter alternative than having the bollard rise and fall on a timer, as it allows for greater flexibility in relation to traffic tailbacks and cars breaking down or stalling at inconvenient moments.

Maxiflow installing new bollard system at Quarry Car Park in Chester

Once the induction loop cabling is laid and connected, another layer of tarmac on top forms the new road surface.

Authorised drivers can raise and lower the bollard by using a keycard or keycard with the control post (D). The post displays two clusters of 25 LEDs which light up green or red to give a clear visual cue to drivers when it is safe to pass through.

Maxiflow installing new bollard system at Quarry Car Park in Chester

With the control post, control box and and bollard in place, the system is complete and ready for use. We would like to once again thank MACS Bollards for their work in bringing this project to completion.

More from the Maxiflow Blog

Drain excavation and repair at Elton Primary School

Elton Primary School in Cheshire

In partnership with Enterprise, the Maxiflow drainage team were contracted to investigate and repair a reported drain fault at Elton Primary School.

Elton is a village in the North West of Cheshire, and the primary school is attended by approximately 300 pupils. The drain problems were severely disrupting day-to-day operations at the school, and when we investigated it was easy to see why!

Drain Excavation at Elton Primary School in Cheshire

Sending cameras along the pipes for a CCTV survey revealed two major issues that were severely impacting the system, in addition to a number of minor structural faults.

Before and after pictures inside playground drain at Elton Primary School in Cheshire

Underneath the school’s playground, a section of the drain had collapsed. Because the integrity of the pipe had been severely breached, the contents of the drain were leaking into the surrounding area, potentially contaminating the local water table, and severely affecting the the pressure of the entire system.

Because this problem was too severe for a simple patch repair, our team excavated down to the defective branch connection through the playground’s tarmac. The pipe and fittings were entirely replaced, and were covered in class B bedding before the hole was backfilled and the tarmac was reinstated.

Maxiflow drain excavation - before and after

The second major issue lay underneath an access ramp. Two of the lateral connections had become separated due to subsidence, affecting the pressure and flow along a critical intersection.

Before and after pictures inside access ramp drain at Elton Primary School in Cheshire

This presented a minor problem as the access ramp is located underneath a canopy, making access difficult for our large excavator. We accounted for this during the planning stage of the project and allowed for a micro digger to also be present on site specifically for this section of the job.

Once the excavation was completed we replaced the connectors on the laterals, making the connection solid once more. It was also neccessary to reset the pipe level, accounting for the ground shifts due to subsidence.

Tarmac replacement after drain repair at Elton Primary School in Cheshire

The minor structural faults identified along the line between two manholes required less invasive repair work. A high-pressure water jetting was carried out inside the pipe, cleaning the line of debris and washing the inner surfaces in preparation for the final stage. Resin patch liners were installed at various points along the line, providing a layer of rigid, waterproof material to reinforce the structural integrity of the pipe.

Drain Excavation by Maxiflow at Elton Primary School in Cheshire

More from the Maxiflow Blog

Sponsor Popsy and Posey’s 12-Month Challenge for the Stroke Association and Spinal Injuries Association

Sponsor Popsy and Posey for the Spinal Injuries Association and the Stroke Association

Maxiflow customer Mr Buckler has brought this very worthy cause to our attention and we wanted to share it with our followers.

Mr Buckler’s daughter Rose and her friend Tracy (known collectively as Popsy and Posey) are undertaking a 12-month challenge to raise money for two excellent charities – the Spinal Injuries Association (SIA) and the Stroke Association.

These charities are very close to the hearts of both women, as explained below:

In 2008, after being rushed in to hospital in the middle of the night Tracy’s Mum (Linda) was eventually diagnosed with Transverse Myelitis. This resulted in Linda becoming paralysed from the waist down. After spending 6 months in hospital and rehabilitation she returned home and began to adapt to life in a wheelchair. Throughout her stay in Southport Spinal Unit the SIA were always there to offer her support and advice.

Rose’s grandfather (John) suffered a stroke in October 2012. This was an awful experience for John and Rose’s gran Hilda who within a matter of moments were facing an uncertain future together and the family faced life-changing decisions. Fortunately John has recovered well, but this has made us all very aware of the fantastic work the Stroke Association do to support stroke victims and fund research that will ensure more sufferers can make the best possible recovery.

Popsy & Posey

To raise money, Popsy and Posey are embarking upon a multitude of challenges each month in the lead-up to their 30th birthdays. From gruelling physical endurance trials and sporting events through to bake sales and coffee mornings, the team are covering all bases in order to reach as wide an audience as possible.

We at Maxiflow have contributed towards a Charity Fundraising Night on Saturday 22nd June at the University of Cumbria (formerly St. Martin’s College) in Lancaster.

For more details, visit Popsy and Posey’s Virgin Moneygiving page or their Facebook page and donate some money towards their cause!

More from the Maxiflow Blog

Date Archive