Step-by-step automated bollard installation at Quarry Car Park in Chester

Maxiflow installing new bollard system at Quarry Car Park in Chester

In a previous blog post, we detailed our installation of a bollard at Abbey Square Gateway. In addition to this high-profile project, Maxiflow were also contracted to carry out the excavation and installation of a new automatic bollard system at Chester’s Quarry Car Park, in partnership with MACS Bollards.

Quarry Car Park is a small, private parking facility off Northgate Street, and is owned by Chester Cathedral. The entrance was previously regulated by a rising barrier arm, which unfortunately proved to be a prime target for vandals.

Faced with the costs and wasted time associated with repairing and replacing the barrier, the Cathedral decided to take a different approach and implement an entirely new automatic bollard system.

Maxiflow diagram of the new bollard system at Quarry Car Park in Chester

The diagram above maps out the area where the new system was installed, and the following points of interest are labelled in the images below:

  1. The bollard itself
  2. The safety induction loops
  3. The control cabinet
  4. The status lights and access control post

Maxiflow installing new bollard system at Quarry Car Park in Chester

The first task involved excavating a trench for the bollard (A). The bottom of the trench was bedded with gravel, and the sides were lined with concrete and cement to give the bollard maximum strength and stability. The bollard itself is housed within a hydraulic mechanism, which enables it to rise and fall smoothly.

To allow for the electrical connections and sensors to be laid along the ground, the existing roadway surface had to be stripped away on either side of the bollard.

Maxiflow installing new bollard system at Quarry Car Park in Chester

During the planning stages, it was noted that ducting installed for the previous barrier arm system could be re-purposed for the bollard. The location marked at (C) connects to the ducts and was chosen to be the site for the bollard system’s control box.

The empty bollard housing (A) in the above photograph demonstrates that the bollard itself is a separate element. If damaged, the bollard can be removed without dismantling the rest of the system.

Maxiflow installing new bollard system at Quarry Car Park in Chester

After smoothing the base, an initial layer of tarmac was laid to protect the underside of the induction loop cabling (B). This cabling is pressure-sensitive and is used to detect the approach and departure of vehicles.

This is an important safety feature, as it ensures that the bollard does not rise up underneath a vehicle. This could damage both the bollard and the vehicle and potentially endanger the driver. Induction loops are a smarter alternative than having the bollard rise and fall on a timer, as it allows for greater flexibility in relation to traffic tailbacks and cars breaking down or stalling at inconvenient moments.

Maxiflow installing new bollard system at Quarry Car Park in Chester

Once the induction loop cabling is laid and connected, another layer of tarmac on top forms the new road surface.

Authorised drivers can raise and lower the bollard by using a keycard or keycard with the control post (D). The post displays two clusters of 25 LEDs which light up green or red to give a clear visual cue to drivers when it is safe to pass through.

Maxiflow installing new bollard system at Quarry Car Park in Chester

With the control post, control box and and bollard in place, the system is complete and ready for use. We would like to once again thank MACS Bollards for their work in bringing this project to completion.

More from the Maxiflow Blog

Tags

5 ways to risk 24 hour drain unblocking 40 Bridge Street Accesswatch Advertising Affiliates Apprenticeship armed forces-friendly organisation Armed Forces Covenant Armed forces day Arriva Article audit Autograss Award Balfour Beatty BAM BBC Bebington Before and After Bentley Birmingham Bishop Heber high school Bollard Bronze award Building jobs in Chester Cadbury Carbon Reduction Car Camera kits. career in construction Carillion Cassiobury Court CCTV Surveying CDHT CDM Regulations Certificate CHAS Cheshire Police Cheshire West & Cheshire Cheshire West & Chester Cheshire West and Chester Cheshire West and Chester Council Chester Chester Cathedral Chester Chronicle Chester FC Chester Football Club Chester Market Chester Scouts Chester Zoo Children in Need Chimneys Christleton Christleton Scouts Christmas Civil and Groundworks Commercial Heating Engineer CompetentRoofer Competition Conservation Considerate construction Considerate Constructors Considerate Constructors Scheme Considirate constructors Coupa Cowboy Builders Crewe CSCS CSCS Card Customers CWAC damaged drains Decorating jobs Defence Employer Recognition Scheme Defra Digital Marketing Apprentice Digital Marketing jobs in Chester Domestic drainage Drainage jobs in Chester drainage survey Drain Clearance Duke of Lancasters Regiment Electrical Services Ellesmere Port energy efficient technology ENGIE Enterprise PLC environmental awareness EPDM Excavation Excavation and Repair Excavation and repairs Ferroli Ffrith Fire Extinguishers Firestone EPDM First Aid kits Flat Roofing Flooding Flooring free flu jabs to our employees Frodsham Galliford Try Graffiti and gum removal Graffiti Removal Granada Green Roof Groundwork jobs in Chester Guest Blog Gutter Cleaning Halton Borough Council Handbridge Health and Safety Health Check Helsby homebuyers drainage survey Home drainage check Honor Goodsite Hoole Hoole Rangers FC How To Insulation Interserve ISO9001 ISO14001 IT jobs in Chester Ivor Goodsite Job opportunities in chester Job Opportunity Jobs in Chester joiner joiner jobs in chester Kingsway Lead Theft Leadwork Littleton Local London Macmillan Cancer Manchester Manchester Cathedral Maxiflow maxiflow jobs MaxiflowLtd: Job Opportunity Maxiflows MaxiVac McAlpine Mechanical & Electrical Meeson Hall Merseyside Mid-Cheshire College Mold Moling (Trenchless pipe laying) NADC National Association of Drainage Contractors National company awards 2016 National Waterways Museum Neston New Service Newsletter NFRC Norland Managed Services Northwich Offers Painting and decorating jobs in chester Painting jobs Patch lining and no-dig-repair Perfect plumbing Plumbing and Heating plumbing jobs in chester Press Release Preventative Maintenance Product Queens Own Yeomanry r Radio RapidRoof re-instatement works RedWeb Refurbishment Report Riello Roman roof Roofing Roofs Royal Welsh Rubber SafeContractor Safety Media Salford saniflo Security Slating Slating and Tiling Slope Smart Barbers Snowdonia Soakaway Social value Solar Panels Solution Sponsorship stop smoking Stoptober Strutt and Parker Supply Chain School Sustainability Sustainable Tattenhall Testimonials The Blues The Contractors Health and Safety Assessment Scheme The Maxiflow.co.uk Stand Tiling Training trombone TV Twitter University of Chester Upton Upton High School Vacuum tankers Vandalism Wales War Memorial Web designer Website wellbeing West Cheshire College Whitby Park Widnes Willaston Winsford Wirral Work Experience Wrexham YouTube